Task #1

open

Air Conditioning

Task #1: Air Conditioning

Added by David Harkins 5 months ago. Updated 5 days ago.

Status:
In Progress
Priority:
Urgent
Assignee:
-
Start date:
13/10/2025
Due date:
31/12/2025 (Due in 3 days)
% Done:

95%

Estimated time:
(Total: 0:00 h)
Room:
Living Room, Office, Utility, Guest Bedroom, Server Room, Master Bedroom

Subtasks 2 (1 open1 closed)

Task #24: Drainage BaseCompleted01/09/202501/09/2025

Actions
Task #34: InstallationNew13/10/202531/10/2025

Actions

Related issues 2 (2 open0 closed)

Blocks Task #8: Fitted WardrobeNew

Actions
Blocks Task #9: Media WallIn Progress17/12/202522/12/2025

Actions

Updated by David Harkins 5 months ago Actions #1

  • Subtask #2 added

Updated by David Harkins 5 months ago Actions #2

  • Subtask #3 added

Updated by David Harkins 4 months ago Actions #3

  • Subtask deleted (#2)

Updated by David Harkins 4 months ago Actions #4

  • Blocks Task #8: Fitted Wardrobe added

Updated by David Harkins 4 months ago Actions #5

  • Subtask deleted (#3)

Updated by David Harkins 4 months ago Actions #6

Updated by David Harkins 4 months ago Actions #7

  • Start date deleted (09/08/2025)

Updated by David Harkins 4 months ago Actions #8

  • Room Living Room, Office, Utility, Guest Bedroom, Server Room, Master Bedroom added

Updated by David Harkins 4 months ago Actions #9

  • Priority changed from Normal to High

Updated by David Harkins 4 months ago Actions #10

  • Subtask #24 added

Updated by David Harkins 4 months ago Actions #11

  • Subtask #34 added

Updated by David Harkins 3 months ago Actions #12

  • Start date changed from 01/09/2025 to 03/11/2025
  • % Done changed from 50 to 10

Deposit Paid Monday 15th Sept.

Updated by David Harkins 3 months ago Actions #13

  • Priority changed from Normal to Urgent

Updated by David Harkins 3 months ago Actions #14

  • Start date changed from 03/11/2025 to 13/10/2025

Updated by David Harkins 3 months ago Actions #15

  • Due date changed from 07/11/2025 to 17/10/2025

Updated by David Harkins 2 months ago Actions #16

  • Status changed from New to In Progress

Updated by David Harkins 2 months ago Actions #17

  • % Done changed from 10 to 40

Updated by David Harkins about 1 month ago Actions #18

  • Due date changed from 17/10/2025 to 18/12/2025

Updated by David Harkins 5 days ago Actions #19

  • Due date changed from 18/12/2025 to 31/12/2025
  • % Done changed from 40 to 95

Just need covers on vents, causing condensation. Server & Living Room